Bampfylde Way (eastbound)
Tuesday 3 May to Thursday 21 July
Closed eastbound from Bonville Road to junction near Hendwell Close, 24 hours a day
New supply
Wales and West Utilities
Caroline Place
Tuesday 3 to Friday 6 May
Three-way signals at Stonehouse Street junction, 24 hours a day
Gas service isolation
Wales and West Utilities
Clittaford Road
Tuesday 3 May to Thursday 21 July
Multi-way signals (rolling) from Bampfylde Way to Rockfield Avenue, 24 hours a day
New supply
Wales and West Utilities
Cobourg Street (outbound)
Tuesday 3 May
Bus lane closed near Tesco, 6.30pm to 11.30pm
Patch repair
South West Highways
Forder Valley Road
Tuesday 3 to Wednesday 4 May (one night)
Road closed between Leigham Roundabout and BP petrol station (access to Wilburt Road maintained), 7pm to 6am
Carriageway changes for Forder Valley works
Balfour Beatty
Mannamead Road
Tuesday 3 to Monday 16 May (not weekends)
Two-way signals near Hermitage Road, 24 hours a day (manually controlled 7am to 7pm)
New supply
Western Power Distribution
Millbay Road
Tuesday 3 and Wednesday 4 May
Two-way signals outside Duke of Cornwall Hotel, 9.30am to 3.30pm (manually controlled if required)
Underground cabling
BT
North Hill Terrace Lane
Tuesday 3 to Thursday 12 May
Road closed, 24 hours a day
New gas service
Wales and West Utilities
North Prospect Road
Tuesday 3 to Friday 6 May
Two-way signals between Laurel Road and Dingle Road, 24 hours a day (manually controlled at peak times)
Connection works
Fred Champion Groundworks Ltd
Randwick Park Road (southbound)
Tuesday 3 May to Tuesday 28 June
Closed southbound from Forresters Road to Plymstock Road, 24 hours a day
Gas main replacement
Wales and West Utilities
Royal Navy Avenue
Tuesday 3 to Monday 16 May
Two-way signals outside number 77, 24 hours a day
Water main works
South West Water
Saltash Road (eastbound)
Tuesday 3 to Wednesday 4 May (one night)
One lane closed on approach to Wolseley Road, 9pm to 5am
Manhole works
Glanville Geospatial Ltd
Tavistock Road
Tuesday 3 to Thursday 5 May (two nights)
Two-way signals between Woolwell Roundabout and Millstones Hotel, 6.30pm to 6am
Fibre cabling
CityFibre
Widey Lane
Tuesday 3 May to Thursday 9 June
Two and three-way signals (rolling), 24 hours a day (manually controlled at peak times at Fort Austin Avenue)
Fibre cable works
CityFibre
Wolseley Road (outbound)
Tuesday 3 to Wednesday 4 May (one night)
No left turn onto Saltash Road, 9pm to 5am
Manhole works
Glanville Geospatial Ltd
Alma Road (outbound)
Wednesday 4 to Thursday 5 May (one night)
One lane closed at Whittington Street junction, 9pm to 6am
Underground cabling
BT
Crownhill Road (eastbound)
Wednesday 4 May
One lane closed from Crownhill flyover to Plumer Road, 6.30pm to 11.30pm
Patch repair
South West Highways
Ridgeway
Wednesday 4 to Friday 6 May
Three-way signals at George Lane junction, 24 hours (manually controlled at peak times)
Ducting
BT
Honicknowle Green/Montacute Avenue
Thursday 5 May to Thursday 16 June
Multi-way signals (rolling) from Honicknowle Lane to Montacute Avenue (phase 1) and from 57 Montacute Avenue to Honicknowle Green (phase 2), 24 hours a day
New supply
Western Power Distribution
Beacon Park Road/Royal Navy Avenue/Wolseley Close
Friday 6 to Saturday 7 May (one night)
Lane closures, with no access to Wolseley Road (outbound), 7pm to 6am
Resurfacing on Wolseley Road
South West Highways
Henderson Place
Friday 6 to Saturday 7 May (one night)
Road closed between Wolseley Road and Melville Road, 7pm to 6am
Resurfacing on Wolseley Road
South West Highways
New Barn Hill
Friday 6 to Tuesday 10 May
Road closed near Hilltop Ranch, 24 hours a day (residents’ access maintained)
Water meter maintenance
South West Water
Wolseley Road
Friday 6 to Saturday 7 May (one night)
Road closed outbound and one lane closed inbound between Wolseley Close and North Down Crescent, 7pm to 6am
Resurfacing
South West Highways
The Barbican
Saturday 7 and Sunday 8 May
Road closures affecting Basket Ope, Quay Road, Southside Street and The Parade, 7am to 6pm
Plymouth City Council
CURRENT/ONGOING WORKS
Alderney Road
Until Friday 20 May
Two-way signals at Inchkeith Road junction, 24 hours a day
Cable overlay works
Western Power Distribution
Belliver Way
Until Wednesday 4 May
Two-way signals opposite Burts Crisps, 8am to 5pm
Gas supply works
CM Utilities
Blunts Lane
Until Saturday 31 December (extended)
Road closed, 24 hours a day
Forder Valley Link Road
Balfour Beatty
Brest Road (northbound)
Until Tuesday 10 January 2023
Road closed northbound from William Prance Road to Derriford Roundabout (emergency service access from Morlaix Drive to Derriford Roundabout maintained under signal control), 24 hours a day
Morlaix Drive Access Improvements
South West Highways
Burleigh Park Road
Until Wednesday 11 May
Three-way signals at Peverell Park Road junction, 24 hours a day (manually controlled from 7am to 9am and from 3pm to 7pm)
Fibre cabling works
CityFibre
Cot Hill (northbound)
Until Friday 20 May
Road closed from Valley Road to Plymouth Road, 24 hours a day
Bridge repairs
Network Rail
Darklake View
Until Wednesday 25 May
Three-way signals at Plymbridge Road junction, 24 hours a day (manually controlled from 7am to 7pm)
New supply
Western Power Distribution
Dean Cross Road
Until Tuesday 28 June
Multi-way signals between Dean Hill and Horn Cross Road, (manually controlled from 7am to 7pm)
Gas main replacement
Wales and West Utilities
Elburton Road/Haye Road/Stanborough Road
Until Friday 27 May
Multi-way signals and various lane closures on all approaches to roundabout, 24 hours a day (manually controlled 7am to 7pm)
New supply
Western Power Distribution
Forder Valley Road
Until Friday 22 July
One lane closed on approach to Novorossiysk Road (heading from Leigham Roundabout), 24 hours a day
Balfour Beatty
Forder Valley Road
Until Friday 19 August
Speed limit reduced to 30mph, 24 hours a day
Balfour Beatty
Forder Valley Road/Novorossiysk Road
Until Saturday 30 July
Two-way signals at junction, with no straight-on access from Novorossiysk Road onto Forder Valley West, 24 hours a day (manually controlled at peak times)
Forder Valley Link Road
Balfour Beatty
Hooe Hill
Until Friday 25 May
Road closed between Belle Vue Road and Sharrose Road, 24 hours a day
New supply
Western Power Distribution
Inchkeith Road
Until Friday 20 May
One-way restriction (no access from Skerries Road towards Clittaford Road) 24 hours a day. Also, two and three-way rolling signals between and at Skerries Road and Rockfield Avenue junctions, 24 hours a day
Cable overlay works
Western Power Distribution
Lockington Avenue
Until Tuesday 17 May
Rolling two-way signals from number 28 to number 130, 24 hours a day
Fibre cable works
CityFibre
Market Road
Until Tuesday 3 May (weekdays only)
Two-way signals outside number 13, 9am to 4pm
Duct-laying
BT
Milehouse Junction
Until Sunday 1 May (nights, no weekends until final weekend)
Road and lane closures on all approaches (inbound and outbound), 7pm to 6am
South West Highways
Miller Way
Until Monday 9 May
Two and three-way signals (rolling) from Thornbury Primary School to Rogate Drive, 24 hours a day (manually controlled at peak times)
Fibre cable works
CityFibre
Morlaix Drive (eastbound)
Until Tuesday 10 January 2023
Road closed eastbound (towards the hospital), 24 hours a day
Morlaix Drive Access Improvements
South West Highways
New George Street
Until Tuesday 3 October 2023 (extended)
Road closed between Old Town Street and Tesco Metro, 24 hours a day
City Centre Improvement Scheme
Mildren Construction
Novorossiysk Road
Until Wednesday 29 June
Speed limit reduced to 30mph between Forder Valley Road and Miller Way, 24 hours a day
Balfour Beatty
Novorossiysk Road (northbound)
Until Friday 22 July
One lane closed from Forder Valley Road to Miller Way, 24 hours a day
Balfour Beatty
Plymbridge Road (northbound)
Until Tuesday 12 July
Alternating lane closures (rolling) from Estover Road roundabout to northern Thornbury Road junction, 24 hours a day
Footway and cycleway works
South West Highways
Plymbridge Road
Until Saturday 31 December (extended)
Road closed from Forder Valley Road to Blunts Lane (access to Poole Farm maintained) 24 hours a day
Balfour Beatty
Portland Square Lane North
Until Monday 9 May
Road closed from Kirkby Place for 25 metres in a westerly direction, 24 hours a day
Cladding renewal
Kier Construction
Sheepstor Road
Until Thursday 30 June
Road closed between Thurlestone Walk and Novorossiysk Road, 24 hours a day
Carriageway, footway, traffic island and verge works for Forder Valley Link Road
Balfour Beatty
Staddiscombe Road
Until Tuesday 17 May
Road closed beween Leyford Lane and Hooe Lane, 9am to 5pm
Blockage location and removal
Gigaclear
Sutherland Road
Until Sunday 8 May
Road closed on rail bridge, 9pm on Saturday to 9.30am on Sunday only (footway open at all times)
Bridge refurbishment works
Network Rail
Tamerton Foliot Road
Until Friday 13 May
Two-way signals at Picklecombe Drive junction, 24 hours a day (manually controlled at peak times)
Resurfacing and footway realignment
WBM Groundworks Ltd
Wilburt Road
Until Sunday 31 July
No right-hand turn onto Forder Valley Road, 24 hours a day
Construction of a new central island on Forder Valley Road
Balfour Beatty
Woolwell Crescent
Until Thursday 5 May
Road closed in one direction from Eco Way to Woolwell Road roundabout, 24 hours a day
Fibre cable works
CityFibre